SA Tenders and Contracts

Display Tender DEM044775

This page displays the details of a tender. See the detailed help in each section for specific information. Detailed Help (Clicking detailed help will open a new browser window)
SA Government logo. Link to Minister's website
 
Oak Valley Remediation Works
Issued by Department for Energy and Mining

Request for Quotation

Tender State: Current Tender
Tender Code: DEM044775
Contract Number: 1819110
Category: Unassigned

Enquiries

Enquiries
Nelson Clayton
84293066

Description

Procurement Overview

Energy Programs, RAES Scheme, during a recent scheduled field trip to Oak Valley and its power station it was reported by the RAES team and including contractor comments on surface staining of the ground with in proximity of the power house compound. The significant staining of the ground currently represents environmental and WHS issues.

 

On closer investigation it was found the original design to have a significant water ingress issue, predominately due to the bunding area around the Diesel Bulk Storage Tank. Directly below the oil stain ground is the waste arrestor tank and soakage pit, the waste arrestor tank is designed to collect waste oil washed of generators and floors by the power station operator during and after servicing/maintenance. The soakage pit is connected to the waste arrestor tank and is designed for water over flow, leaving the contaminated oil in the waste arrestor tank as designed.

 

However, the current bunded area around the Diesel Bulk Fuel Storage Tank comprising of concrete floor and walls is connected directly to the waste arrestor. On heavy rains the water collected in the bunded area far out ways the amount of water able to be held in the waste arrestor tank and soakage pit. This is the majority cause of the heavy contamination of the ground and effectiveness of the waste arrestor tank and soakage pit due to the significant over flow.

 

Following the concerns of contamination to the surface, Greencap was commissioned to conduct a Limited Soil Investigation at the power station. The objective of the investigation was to assess the nature and extent of hydrocarbon contamination of soils in this area. The investigation was conducted on 11 and 12 September 2018 under the supervision of an experienced Greencap environmental field scientist

 

Greencap’s report recommends that when new infrastructure is installed, remedial works are carried out to remove the soils with the most significant impacts. Impacted soils should be removed from the site and disposed of at a licensed facility. It is noted that Greencap has not undertaken formal classification of the soils, but based on the current data set, they would likely be classified as high-level contaminated soils and may require treatment prior to disposal

Project Requirements

RAES will require a project management solution to plan and execute the removal of contaminated soil and required infrastructure to ensure there is not a repeat of contamination in the Oak Valley Power Station compound, by:

  • Reviewing the Greencap report

  • Remove the contaminated soil to a place licensed in receiving hi-level contaminated soil

  • Replace the trade waste arrestor tank

  • Replace the soakage pit

  • Install a lean too/veranda (overhead protection from the weather elements) over the grated bunded area

  • Decommission existing drainage services and the Diesel Bulk Storage Tank bunded area, and

  • Install a new Double Bunded Diesel Bulk Storage Tank

  • Install a new diesel pump set and reticulation system, and

  • Provide a detailed end of project report.

Specification Documents

Download Now
Oak Valley Remediation Works Request for Quote (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 1 Oak Valley Power Station - Limited Soil Investigation (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 2 Photos (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 3 Oak Valley Powerhouse Hydraulic Services 1439-me-2002 (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 4 Oak Valley Lean to Construction (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 5 GNA REVISED Diesel Fuel Storages and Pipe Work Specifications V 1.7 b (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 6 RAES Standard Fuel Diagram (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 7 Oak Valley Power House Site Plan (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 8 Document checklist (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 9 WHS Contractor Pre-Qualification (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 10 RAES Power Station Functional Design Specification_Fuel System (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 11 Oak Valley Powerhouse Plans and Elevations (Ver 1 - 12 Feb, 2019)
Available by Download
Attachment 12 Tank Junction Box (Ver 1 - 12 Feb, 2019)
Available by Download
You must be logged in to download documents.

Responses

Tender closes at 5:00 PM Adelaide time 8 March 2019

Click here to submit an electronic response

You must be logged in to submit a response.

Survey

The Issuing Agency has confirmed that the supplier feedback tool can be used to provide feedback on your experience with this tender process. Refer to additional information on the home page.
Click here to access the survey

Downloaded documents may require one of the following free viewers to be viewed on your computer:
Get Acrobat Get Winzip Get Word